Analysis: How the UK plans to reach clean power by 2030
We’re already helping to speed things up and unlock the investment needed by cutting red tape, fast-tracking grid expansion and getting more clean power projects connected. The action plan outlines steps to expand and improve the electricity grid, saying that a failure to strengthen it "risks holding back our energy security, economic growth and other important infrastructure with lengthy delays”. “These investments will protect electricity consumers from volatile gas prices and be the foundation of a UK energy system that can bring down consumer bills for good. The plan describes this as “once-in-a-generation levels of energy investment” that will “spread…the economic benefits of clean energy investment throughout the UK”.
It asked for different pathways to reach this goal, as well as key requirements for electricity grids, high-level analysis of costs and benefits, and suggested actions to get on track. That’s because the UK is increasingly reliant upon intermittent renewables (such as wind and solar) to generate the required amount of power. DPS not only provides enough renewable electricity to power five million households – the number of homes in Scotland and Wales – but also delivers essential grid balancing services. We’re particularly keen to see new measures in the upcoming Industrial Strategy to support investment in clean energy supply chains, as well as a final decision on market reform to provide certainty and confidence.” The government response to the 2021 Committee on Climate Change (CCC) progress report to Parliament in reducing UK this document from GOV.UK emissions is published alongside this strategy.
“While the state must play a role as system architect, markets are, and will remain, central to the development, delivery, and operation of the power system.” First introduced in 2002, the UK-wide renewables obligation (RO) scheme currently supports around 30% of the UK’s electricity supply. Beyond the CfD reforms, the action plan includes a number of commitments to improve renewable energy project delivery.
The proposals also look to increase the number of projects that can potentially bid for Government power contracts next year, as well as setting out a forward programme of CfD auctions, which could further boost investment in the sector. The plan also rightly focusses on integrating renewables into the future energy system, such as by accelerating the deployment of flexibility and storage solutions, including long and short duration storage, green hydrogen and interconnectors. Member States each have different individual targets to allow this overall target to be met, and they are obliged to provide detailed roadmaps describing how they will meet their legally binding target.
To support greater flexibility in the electricity system, the government plans to publish a “low carbon flexibility roadmap” in 2025. “We plan, therefore, to announce the final decisions on REMA and the timetable for their implementation, particularly in relation to wholesale market reform and any transitional or legacy arrangements, before the AR7 auctions open, giving investors clarity for prospective bids.” In order to limit the impact of any changes on the investment needed in new clean power capacity, the government pledges to “align” the process with the next CfD auction.
The National Energy System Operator (NESO) believes CP2030 is achievable – so long as everything that needs to happen (and it’s a long list) occurs in sequence and on time. Following up on its pre-election manifesto commitments, the incoming Labour Government quickly moved to establish Great British Energy and then published the Clean Power 2030 Action Plan. The SEA addressed key themes such as climate change, health, natural resources, biodiversity, cultural heritage, landscape, and society, and assessed impacts for four scenarios. Each Member State is required to ensure that the public is given early and effective opportunities to participate in the preparation of the draft integrated national energy and climate plan. Under rules in this regulation, all member states were required to prepare a draft (by 2020) of a 10-year integrated national energy and climate plan (NECP) for the period from 2021 to 2030, charting how they aim to meet the EU’s energy and climate targets for 2030. Annex 36 outlines the requirements for National Renewable Energy Action Plans and the more recent National Energy and Climate Plans, including the assessments each plan must include.
We’re taking a tough line and will hold the industry to account when it comes to the sector delivering on time and on budget." An “unprecedented expansion” is therefore needed to deliver decarbonisation, energy security and affordability, with around twice as much new transmission infrastructure needed by 2030 as has been delivered in the past decade. The government’s action plan sets out its approach to delivering this across a series of key areas. This indicated it could be delivered with similar costs to today, with scope for lower electricity costs and bills by 2030 as wider changes are taken into account.” “In their advice, NESO set out their analysis of potential impacts of delivering clean power on electricity costs in 2030.
To enable clean power by 2030, most new transmission grid and offshore wind projects will need all relevant planning permissions to be in place by 2026, the report notes. It states that the planning system is “not working at the pace required” to meet the 2030 target and that this “urgent need for change” necessitates “a wide-ranging reform programme”. One day before the action plan was released, the government published its response to a consultation on proposed changes to the National Planning Policy Framework (NPPF). Given their size, all three solar sites are considered nationally significant infrastructure projects (NSIPs), and as such require a development consent order from the energy secretary, as opposed to planning permission from the local planning authority.
In fact, the Government expects these natural resources to provide, by 2030, the majority of the country’s electricity. One was for the more established technologies, such as solar PV, onshore wind, and landfill gas (LFG). Since it’s a ‘reverse auction’, the bidders try to undercut their rivals resulting in the lowest priced projects being awarded CFDs.